By Quacy Barry, founder of BackHome Developments Co. Inc., the company behind Pristine Ridge Homes, with more than 20 years building homes in Canada and Guyana. Last verified November 2026. US dollar figures at GYD 200 to US$1.
Short answer: A finished house in Guyana costs about GYD 28,000 to 32,000 a square foot at standard specification, 33,000 to 42,000 mid-range, and 45,000 and up for high-end. Our four fixed-price homes run from GYD 33M (US$165,000) for 1,000 square feet to GYD 72M (US$360,000) for 2,200, with drawings and permits included. Land, site works and the yard sit outside every one of those numbers.
What a finished house costs, home by home
These are our published prices. They don’t move once your selections are made.
| Home | Size | Bedrooms and baths | Price | Per sq ft |
|---|---|---|---|---|
| CORE | 1,000 sq ft, one storey | 2 bed, 2 bath | GYD 33M (US$165,000) | GYD 33,000 |
| VERANDA | 1,400 sq ft, one storey | 3 bed, 2 bath | GYD 46M (US$230,000) | GYD 32,900 |
| LANDING | 1,800 sq ft, two storeys | 3 bed, 2.5 bath | GYD 54.5M (US$272,500) | GYD 30,300 |
| CANOPY | 2,200 sq ft, two storeys | 4 bed, 3.5 bath | GYD 72M (US$360,000) | GYD 32,700 |
Each price covers the house built to specification, the architectural and structural drawings, the CH&PA permits, the exterior lighting and your finish collection. You pay the CH&PA fees when we submit, and they come back to you on the first construction payment.
Why the smallest house costs the most per square foot
Look at the last column. CORE is the cheapest house and the most expensive per square foot.
A 1,000 square foot house still needs a full kitchen, two bathrooms, a water system, an electrical panel and air conditioning. None of that shrinks with the floor. So when someone quotes you one rate per square foot for every size of house, ask what happens to the small one. Either the small house is underpriced or the big one is padded.
Why the numbers you’ve heard are so far apart
Your cousin says he built for half this. He probably did. The question is where his number stopped.
On a 2,852 square foot two-storey we priced at Golden Grove on the East Bank, the house was 29% paid for when the roof went on. The other 71% came after: windows, doors, wiring, plumbing, ceilings, tile, the kitchen, the bathrooms, the paint. A quote that stops at the roof is a quote for less than a third of a house.
So before you compare two numbers, ask each builder one question. What does this number stop at? Then get the answer in writing.
What sits outside the price
Every builder’s price leaves something out. The honest ones tell you what before you sign. Ours leaves out four things.
Land. Separate from the build, and so is getting it into your name before a bank will lend against it.
Site works. On a raw lot, the fill, the fence, the driveway and the bridge over the drain run GYD 8.5 to 16 million. Our yard packages start at GYD 11M (US$55,000).
Piling. None of our four homes normally needs it. On swamp or filled land it can, and on an 1,800 square foot two-storey that runs about GYD 9 to 13 million. A soil test tells you before anyone pours anything.
Your contingency. Keep 10% aside. Our price is fixed, so that money is for what sits around the house.
What your money actually builds
Here’s the arithmetic I’d want someone to do for me.
Say you have GYD 60M between savings and the bank, and a raw lot. Take 10% off for contingency and you have GYD 54M. Take the yard off, GYD 11 to 16M, and you have GYD 38 to 43M for the house.
That’s CORE, with room to spare. With GYD 60M it’s tempting to look at LANDING. On a raw lot, LANDING is the house that stops at the roof.
If your lot is already filled, fenced and drained, the same GYD 60M finishes VERANDA. And the bank’s approval isn’t your budget either. Here’s why those two numbers differ.
How long it takes
A single-storey home takes about 8 to 12 months. A two-storey takes up to about 18. Start just before the May to June or December to January rains and you lose weeks you can’t buy back.
Questions people ask
How much does it cost to build a house in Guyana in 2026?
About GYD 28,000 to 32,000 a square foot at standard specification, finished. Our fixed-price homes run from GYD 33M (US$165,000) for 1,000 square feet to GYD 72M (US$360,000) for 2,200. Land, site works and the yard are extra.
How much does a 3-bedroom house cost to build in Guyana?
Our 3-bedroom homes are VERANDA at GYD 46M (US$230,000) and LANDING at GYD 54.5M (US$272,500). Here’s the full 3-bedroom breakdown.
Is a two-storey house cheaper to build?
Per square foot, yes, because two floors share one foundation and one roof. LANDING and CANOPY both come in around GYD 30,000 a square foot or less. The total is still higher because the house is bigger.
Does the price include land?
No. We build on your land, or we help you find a lot and build on it. The price is the house, the drawings and the permits.
What’s the first step?
The Build Package, GYD 500,000 (US$2,500), credited to your build. It includes the site assessment anywhere from Berbice to Linden.
Find the home your number finishes
Answer a few questions and you’ll see which of the four homes your budget finishes, and what sits outside the price, before you talk to anyone. Find your home or start your build.